The design of the heating installation is based on the greenhouse surface area of 72.000 m². The greenhouse expansion consists of 16 climate zones. Each climate zone is provided with a tuberail, grow tube and gable heating. The greenhouse consists of 4 climate zones for the snow heating.

We deliver and install 3 traditional 3 pass boiler, make: Crone, 1 heat storage tank 4.000 m³ including a nitrogen expansion system.

We will build a manifold Ø 610 suitable for the complete project. On this manifold we’ll build 3 transportation line pump groups, 1 connection for irrigation heating, 1 connection for irrigation heat exchanger, 1 connection for air heaters, 1 connection for corridor heating, 2 spare connections DN150. The manifold will be high mounted.

The greenhouse is provided with a CO₂ dosing installation connected to the flue gas condensers of the gas fired boiler in the boiler room.

Cooling installation

We will deliver and install 7 chillers outside the technical room. In the technical room a manifold will be delivered and placed for 4 zones. In the greenhouse 160 cool units will be installed.

The heating and cooling installation will be insulated.


Update March 2019 Fase 2