Tweed
Niagara o/t Lake
Ontario
The design of the heating and cooling installation is based on the greenhouse surface area of 21.298 m².
We will deliver and install 2 traditional 3 pass boilers, make: Crone and a 600 m³ hot water storage tank including nitrogen expansion system.
The boiler room is prepared with a heating manifold incl. spare connections for the new phase. The new greenhouse project consists of a total of 8 climate zones. In the greenhouse each climate zone is provided with a floor heating, a hoist heating and gable heating system
The greenhouse is also provided with a CO₂ dosing installation connected to the flue gas condensers of the gas fired boilers in the boiler room.
Cooling installation
We will deliver and install 2 chillers outside the technical room. In the technical room a manifold will be delivered and placed for 8 zones. In the greenhouse 72 cool units will be installed.
The heating and cooling installation will be insulated.